Feasibility Study of the Water Supply to Large Maputo, Including an Executive Project

Image

In the Feasibility Study phase, CONSULTEC was responsible for the following activities:

  • Collection and analysis of information on the current state of the water supply system in Maputo;
  • Participation in the study of comparison of several options on how to bring water to the city of Maputo.

In the Executive Project phase:

  • Structural design of more than thirty different buildings and structures.

Design of electrical components:

  • Connection to the main grid, transmission lines and electrical installations;
  • Coordination of environmental studies with the company that was developing the environmental impact study;
  • Collaboration in economic and financial studies;
  • Preparation of budget estimates and lists of quantities for some components of the work.

 

In the Executive Project phase:

  •  Structural design of more than thirty different buildings and structures.

 

Design of electrical components:

  •  Connection to the main grid, transmission lines, and electrical installations;
  •  Coordination of environmental studies with the company that was developing the environmental impact study;
  • Collaboration in economic and financial studies;

Preparation of budget estimates and lists of quantities for some components of the work.

    1/1
INFORMATION
Activity
Water
Location
Maputo Province
Year
02/2017
Client
FIPAG - Fundo de Investimento e Património de Abastecimento de Água
Associated companies
COBA
State
Completed
TEAM
Deputy Project Director
Carlos Caupers
Electricity Component
Dasneiro Mataveia
Environmental Component
Vera Ribeiro

PROJECT SHEET